Skip to main content
All CollectionsUsing HiveProjects
Understanding Auto-scheduling options
Understanding Auto-scheduling options

Learn how to use auto-scheduling in your gantt chart

Erin Gouveia avatar
Written by Erin Gouveia
Updated over a year ago

Auto Scheduling Settings: Strict vs. Not Strict Scheduling

You can manage exactly how you want the dependencies to perform by choosing either 'Off', 'On', or 'Strict' or dependency relationships for a project on the 'Auto scheduling' settings page under the 'More' menu.

Additionally, the default auto-scheduling setting for new projects can be set on the Workspace Settings page by Admins. Note: Project Template auto-scheduling settings will override the default for new projects.

'Off': Duration and date changes to dependency and predecessor actions will not adjust other actions in the project.

'On': This will favor the dependent action's start date rather than the dependency link itself, meaning that the preceding action can move forward in time without affecting the dependent action. Only once the predecessor has passed the start date of the dependent action, will the dependent action move forward.

Additionally, if a predecessor action is completed in a shorter duration than planned, the dependent actions will not move forward automatically to account for the shorter duration adjustment.

'Strict': Strict scheduling (or 'ASAP' scheduling) means that all actions move together, no matter which direction they are moving. This is also where you can set strict lag or gap time. If a predecessor action is completed in a shorter duration than planned, the dependent actions will move forward automatically to account for the shorter duration adjustment.

Create the dependencies as normal. To create lag time, either click on the dependency link itself or write the advanced predecessor in the 'Predecessor' column. Now when one action moves forward or backward in time, they will all move together.

Pro-tip: when updating auto-scheduling settings, an update to the project is needed in order for the updated setting to apply. Slightly drag the action card's bar to trigger the update.

Additionally, the predecessor column in Gantt is also where you can write advanced dependency functions (FS, FF, SS, SF + "Xd"). Use the formulate to add days of "lag" to the previous dependency. Like, "1.1FS+2d".
โ€‹
When it comes to dependencies you can use in your Gantt projects, there are 4 types of those:

  • Finish-to-start (FS) - You cannot start action B before action A is completed
    This type of dependency can be applied when you need one task to be finished before the next one can be started.

  • Finish-to-finish (FF) - You cannot complete action B before action A is done

    If you don't want to finish an action before the preceding one is completed, this type of dependency will be the one to go for.

  • Start-to-start (SS) - You cannot start Action B before action A starts

    Sometimes you might need to have one action start before letting the following one kick off. This type of dependency will allow you to do that.

  • Start-to-finish (SF) - You cannot complete action A before action B starts

    With this type of dependency, the preceding action cannot be marked as completed up until the following action starts.

You may also set the default Gantt auto scheduling for the workspace, in the Workspace Settings page.
โ€‹

Did this answer your question?